Title: ESTABLISH APPROPRIATIONS TO AWARD A CONSTRUCTION CONTRACT FOR THE VILLAGE VIEW PARK PROJECT AND RELIANCE ON PREVIOUSLY ADOPTED MND (DISTRICT: 5)
Attachments: 1. 2023-07-19-Village-View-BL Strikeout-Underline, 2. 2023-07-19-Village-View-BL Final Clean, 3. Village View Approval Log, 4. Village View A 72 Form 1, 5. Attachment A Vicinity Map, 6. Attachment B CEQA Environmental Review Update Checklist Previous Mitigated Negative Declaration, 7. 07192023 ag05 Public Communication 1, 8. 07192023 ag05 speakers, 9. 07192023 ag05 Minute Order

DATE:
July 19, 2023
05

TO:
Board of Supervisors

SUBJECT
Title
ESTABLISH APPROPRIATIONS TO AWARD A CONSTRUCTION CONTRACT FOR THE VILLAGE VIEW PARK PROJECT AND RELIANCE ON PREVIOUSLY ADOPTED MND (DISTRICT: 5)

Body
OVERVIEW
In March of 2020, the Department of Parks and Recreation (DPR) purchased 6.8 acres of future parkland to the east of the existing Fallbrook Community Center to address a lack of access to nature and active recreation opportunities in the community of Fallbrook. The Fallbrook Local Park Project (Project), now known as Village View Park, was catalyzed by over a decade of community requests to use Park Land Dedication Ordinance (PLDO) funding to acquire and develop active recreation opportunities in Fallbrook and will feature amenities prioritized by residents throughout the public engagement process. This project has received funding from several grants totaling $4,322,000, which includes the Community Development Block Grant $2,122,000, the California Department of Parks and Recreation's (CDPR) Office of Grants and Local Services (OGALS) Statewide Park Program $1,200,000, and the California Natural Resources Agency's (CNRA) Urban Greening Program $1,000,000.

On October 20, 2021 (7), DPR brought the project to the Board of Supervisors (Board) to approve the advertisement and award of a construction contract for Village View Park, and the Department of Purchasing and Contracting took the project out to bid on May 26, 2023. Due to significant construction cost escalation related to labor and material shortages and inflation, the lowest responsive and responsible bid for the contract came higher than expected, at $10,775,070. The total estimated cost of construction is now anticipated to be $13,234,566, $11,334,566 which includes a limited contingency, construction management, cultural and biological monitoring, and inspections. This exceeds the existing project budget of $7,848,000. Several grant agreements for the project specify feat...